The project scope involved removing old underground utilities and installing new utilities including laying a total of 695 feet of reinforced concrete pipe, laying 3,300 linear feet of 4- to 5-foot-deep trench drains, reworking roadways into the site, and putting in 3.5 feet of base before laying joint enforced pavement and roller compacted pavement, which was self-performed. The total combined area of two yards is 17 acres.
McCarthy also recently began construction on Wharfs 4 and 5 at Barbours Cut, having already completed Wharfs 1, 2, and 3. The project scope includes reconstruction of the ship dock, with a total length of 1,333 feet, adding additional support piles for new, 100-foot gauge ship-to-shore cranes, updating electrical infrastructure, and putting in a new water line, as well as demolishing and rebuilding several support buildings on site. McCarthy will also self-perform all concrete-related work.
McCarthy completed the Barbours Cut Terminal Container Yard 3 North in April 2022, in addition to Container Yards 1 North and 2 North in 2020. Wharfs 4 and 5 are scheduled to be completed in early 2026.